FIR Program Inspections

← FIR: Field Issuance Remodel Program

Breadcrumb: Home > Permitting & Development > FIR Program Inspections

Source: FIR Program Inspections ↗ Last modified: Sun, 19 Apr 2026 20:07:04 GMT


Label: Information

Schedule inspections

After a permit has been issued, call or email your FIR inspector to schedule inspections. Do not use the IVR system to schedule. Do not use DevHub to schedule.

When you request an inspection, provide the following information:

  • Permit Number OR Site Address
  • Type of inspection requested
  • Date and time requested
  • On-site contact person and phone number

Give your inspector advance notice of 24-48 hours.

Inspectors can accommodate most inspection requests. If your FIR inspector is not available, contact the FIR Main phone at 503-823-6691 or email ppdfirpermits@portlandoregon.gov, and another inspector will be assigned.

As a FIR contractor, you are the main point of contact for inspections and must also schedule all inspections for your subcontractors.

Cancellation policy

Cancellations within 24 hours of the scheduled inspection. You will be charged a minimum 1/4 hour charge (15 minutes).

The inspector is en route when an appointment is canceled. You will be charged a minimum of 1/2 hour charge or more depending on distance.

Inspection results

You or your customer can check the status of an inspection result on PortlandMaps ↗. Please allow for up to 24 hours for results to post.

Permit revisions

Learn how to apply for permit revisions through the FIR Program.