Interim noise control rule on construction activities due to heat

← 15

Breadcrumb: Home > Permitting & Development > Noise Program > News > 15 > Interim noise control rule on construction activities due to heat

Source: Interim noise control rule on construction activities due to heat ↗ Last modified: Sun, 19 Apr 2026 20:08:13 GMT


Label: News article

Published

May 15, 2023 9:00 am

This interim rule will be in effect for 180 days.

Construction companies choosing to begin work early due to heat must email the Noise Control Office at variances@portlandoregon.gov and notify neighbors within a 500-foot radius of the construction site about the planned 6 a.m. start during high heat within 3 to 5 days.

This interim rule excludes pile driving, concrete saws, jackhammers, rock crushers and Vactor trucks.

This interim rule does not apply to Sundays and legal holidays.