Applicant ProjectDox quick start guide
Breadcrumb: Applicant ProjectDox quick start guide
Source: Applicant ProjectDox quick start guide ↗ Last modified: Fri, 17 Apr 2026 20:01:54 GMT
1. Complete your permit application.
Work with your Process Manager or submit your completed permit application online through DevHub ↗.
2. Prepare files for submittal.
Plans must meet specific conventions.
- Plans are not to exceed 36 X 48 E/O
- Each drawing must on a single sheet. Multiple page drawings are not accepted.
- Follow detailed file naming guidelines noted below.
- Add required third-party verified digital signature or seal to the project submission as needed.
- Do not password protect, encrypt or secure files.
3. Receive an email invitation from ProjectDox@portlandoregon.gov.
4. Upload project plans and documents to ProjectDox.
Quick Start to File Naming Standards:
- File names should reflect the file’s content.
- Limit the file name to 50 characters or fewer. Use abbreviations when necessary.
- Follow these rules when using special characters.
- Do use “.” (period), “&” (ampersand), and “ – “ (dashes).
- Do NOT include any special characters including “_” (underscores), %, #, “,” (commas), etc.
- Example: 005 A101 THIRD FLOOR PLAN
5. Complete the Upload Task in ProjectDox.
- Select the Tasks tab.
- Select the Applicant Upload Task associated with your project.
- Select the box confirming you have completed this task and are ready to submit.
- Select Upload Complete – Notify the City of Portland.
6. View Project Status and Comments.
View project status and review comments at any time by opening a project and selecting the Status tab and Reviews tab in ProjectDox.
7. Prepare and upload corrected files.
- Select the Tasks tab; select the Applicant resubmit Task associated with your Project.
- Proceed with uploading the corrected files. Please be sure to submit responses to all comments.
- Use the exact same file name on revised files as the original file name. When you are successful, you see a “V” followed by a number next to the newly uploaded file name.
Module 5: Resubmit (YouTube) ↗
8. Complete the Applicant Resubmit Task.
Once all corrected files are reuploaded, you are ready to resubmit to the City.
- Scroll down on the Applicant Resubmit Task eForm.
- Check off the boxes confirming you have completed this task and are ready to submit.
- Select "Complete to notify the City of your completion".
9. Download reports about different aspects of your project.
Generate reports from the Reports tab in a project.
- The Plan Review - Workflow Routing Slip report shows the sequential progress of tasks through the review process.
- The Plan Review - All Unresolved Comments report lists all unresolved review comments for a review cycle.
- The Plan Review - Department Review Status report shows the status of all reviews in a project.
- The Current Project - All Uploaded Files with Sheet Sizes report lists all uploaded files in a project along with their sheet sizes.
10. Review cycles continue until project is approved.
Once the Applicant Resubmit Task is complete, City staff review the corrections.
- The review cycle continues until all the requirements are met.
- ProjectDox@portlandoregon.gov sends an email when the project is approved, and issuance fees are due.